"Purple Rain"

I know, I know, once again I am late as it is now three weeks since my last update on Sunday 3rd September. I've been a trifle busy and had much frustration in terms of keeping contractors both active on my site and aligned, plus booking others in, so I can get the house to lock up and certain critical jobs completed before running into cold weather. Before I start a write up of the last three weeks, the photo below is the house as it was at the end of my last update with the roof over framing in place ready for the subsequent spray foam insulation. Monday 4 September, the day after I last published an update, was yet another statutory (public) holiday for Labour day, so no activity. Next day I had two contractors on site, my electrician, and fireplace installers. The electrician was fitting LED pot lights above all three covered decks (front, over garage and rear loft bedroom deck), and a few internally above the Great Room. These are fitted through the 2" tongue and gr...